In 1999, construction began on the $1.2 billion McNamara Terminal at the Metro Airport in Detroit, Michigan. Certain damages were claimed under the builders risk insurance policy, as having caused delay in the completion of the project. After suit was filed, Lisa Enloe and Jonathon Held were retained by the builders risk insurer to provide both a schedule and cost analysis. They co-authored an expert report, were both deposed in the case, and appeared as witnesses at a mediation in which the case was settled.